Building permit – ordinary procedure
Building-permit workflow in the City of Zurich under the cantonal Planning and Building Act, including public notice, objections, decision and appeal.
Steps (textual)
- Building project plannedStartApplicant
- Prepare building applicationInputApplicant
Plans, project description, evidence of energy/acoustics/statics and application forms.
⏱ 4–12 weeksCHF 5'000–50'000 - Submit application (eBaugesuche)InputApplicant⏱ 1 business daysCHF 300–2'000
Prüfung, ob das Gesuch vollständig und bearbeitbar ist.
⏱ 5–15 business days- Submit missing documentsLoopApplicant⏱ 1–6 weeks
- ⏱ 20 business days
- Objections filed?DecisionObjectors (neighbours)
- ⏱ 4–16 weeks
- Cantonal specialist reviewProcessCantonal specialist offices⏱ 4–12 weeks
- ⏱ 6–20 weeks
- ⏱ 1–2 weeks
- File appeal?DecisionApplicant
- Appeal proceedingsProcessBuilding Appeals Court⏱ 6–18 months
- Construction may begin (after legal force)EndApplicant
- Application denied (final)EndApplicant